Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG PIPING FLUSH
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2015 | FIRE SPKLR - UG PIPING FLUSH | Approved | Had to go out twice on this day to complete flush, in the morning (0830 hrs.) flush line set up was not safe, told contractor to call me back when they set up a safe way to flush. In office (1230 hrs.) have a message on my phone contractor call and asked if I would come back out to due flush. - 1 minute 30 seconds flushed - Extra inspections will be added on. | |
| 04/30/2015 | FIRE SPKLR - UG PIPING FLUSH | Cancelled | IVRS - RI canceled | |
| 04/30/2015 | FIRE SPKLR - UG PIPING FLUSH | Denied | Plactic wrap and wire traser in place | |
| 04/29/2015 | FIRE SPKLR - UG PIPING FLUSH | Denied | Need 36" depth for the fire line because of traffic driving over the line, contractor asked if they can us a slurry to meet the requirements for 36 inch burial I advised if they get an engineer to write a letter stating that slurry poured over the piping will meet the requirements for 36 inch burial depth then this will be approved. Also advised the contractor to ploy-plastic cover all piping so as the slurry can't damage the piping. 200 PSI test for 2 hours approved if slurry is approved an engineer as equal to 36 inch burial depth. |
|
| 04/27/2015 | FIRE SPKLR - UG PIPING FLUSH | Denied | According to the approved plans piping bury to 36" as of today only 28" need to bury 36 inches |