Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2015 | FIRE SPKLR - FINAL | Approved | ||
| 02/26/2015 | FIRE SPKLR - FINAL | Denied | 1. Sprinkler inspections & 5 year check valve inspections are pass due need reports for all 4 risers. 2. Sprinkler escutcheons are not fitting correctly need tight fit to the ceiling no openings aloud. 3. PIV (post indicator valve) not working properly when shut down water leaks by, need to repair or replace PIV. 4. Flow switch for fire bell not work wiring pulled out and there is no WMG (water motor gong) need this repaired. 5. Need a fire alarm monitoring system install to the sprinkler system. 6. Taped upright sprinkler heads in the stock and one painted head in the bathroom, need to correct. |