Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 05/15/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Approved |
IVRS - Inspection :* |
| 05/04/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |
| 04/29/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 04/28/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |
| 04/28/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
PROVIDE CLEARANCE TO COMBUSTIBLES FROM FLUE PIPING AT BOILER AND WATER HEATER |
| 04/23/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |
| 04/23/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
GAS PRESSURE TEST AT FUEL ISLAND BUILDING OK |
| 04/22/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 04/22/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
CONTRACTOR CANCELED BY PHONE |
| 04/14/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |
| 04/14/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
4" GAS AT BUILDING #10 PRESS TEST OK, EXCEPT CONNECTION TO EXISTING |
| 04/03/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |
| 04/03/2015 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
PRESSURE (3 PSI) OK AT WASH BAY ONLY. PRESSURE REGULATOR CALLED FOR ON PLANS NOT INSTALLED AT THIS TIME |