Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2015 | ENGINEERING - FINAL | Approved | ||
| 12/08/2015 | ENGINEERING - FINAL | Approved | PER APPROVAL SHEET | |
| 12/07/2015 | ENGINEERING - FINAL | Continued | 1) INSTALL TRASH ENCLOSURE GATES 2) COMPLETE ADA PARKING CHANGES 3) INSTALL OVERHEAD POLES IN DRIVE AREA 4) COMPLETE LANDSCAPING 5) INSTALL BIKE PARKING PER PLAN |
|
| 11/20/2015 | ENGINEERING - FINAL | Continued | 1) PRIOR TO APPROVAL FOR ENGINEERING FINAL, MEET ALL REQUIREMENTS LISTED UNDER PERMIT# DP14-0246. 2) COMPLETE ALL SITE WORK PER THE APPROVED PLANS 3) FOR PARTIAL APPROVAL, ENSURE REMAINING CONSTRUCTION IS SEPARATED FROM PUBLIC ACCESS, ENSURE NO LIFE SAFETY CONCERNS ARE PRESENT. |