Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2016 | PLUMBING - PROGRESS | Approved | IVRS - Inspection :* | |
| 01/22/2016 | PLUMBING - PROGRESS | Partial Approval | 3RD FLOOR CLOSET FLANGES OK | |
| 12/22/2015 | PLUMBING - PROGRESS | Partial Approval | CLOSET FLANGE ON 1ST FLOOR OK | |
| 12/07/2015 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 11/24/2015 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 09/17/2015 | PLUMBING - PROGRESS | Partial Approval | 1. PLMBG ROUGH ALL FLOORS G.C A TLTRU E AND GL Z-NORTH 2. MECH AT EAST CORR 1ST FLOOR OK |
|
| 08/18/2015 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/18/2015 | PLUMBING - PROGRESS | Partial Approval | 1. PLUMBING ROUGH IN WALLS NORTH RESTROOMS 2ND FLOOR OK 2. GROUT OK 5TH LIFT |
|
| 08/13/2015 | PLUMBING - PROGRESS | Partial Approval | ROOMS 101,102,102 10 ' TEST OK. BASEMENT GRID LINE A TO D, 1 TO 4 TEST OK. | |
| 08/07/2015 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/07/2015 | PLUMBING - PROGRESS | Partial Approval | ??? PUMP DISCHARGE UNDER SIDEWALK OK |