Inspection Status: Approved
Inspection History: FIRE - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/07/2015 | FIRE - FINAL | Approved | PLANS HAVE BEEN CHANGED TO INDICATE 2 REQUIRED EXITS BUT OCCUPANT LOAD IS NOW 30 AND RATED CORRIDOR IS NOT REQUIRED | |
| 04/29/2015 | FIRE - FINAL | Denied | 1. Per IFC section 1018 CORRIDORS; Occupant load on approved plans state 34, over 30 then all corridors shall be 1 hr. fire rated with 20 min fire doors that are self-closing and latch and have smoke gaskets installed. 2. According to IFC sections Tables 1014.3 & 1021.2 travel distances for one exit is 75 foot on the cover page of the approved plans shows 98 feet travel distance, will need two exits. 3. Will need to remove in the code analysis section about this building having a sprinkler system and remove the section for DEFERRED SUBMITTAL "FIRE SPRINKLERS", or you can add a sprinkler system (under approved permits and plans) to the building a forgo the fire rated corridors. |
|
| 04/27/2015 | FIRE - FINAL | Denied | 1. Per IFC section 1018 CORRIDORS; Occupant load on approved plans state 34, over 30 then all corridors shall be 1 hr. fire rated with 20 min fire doors that are self-closing and latch and have smoke gaskets installed. 2. IFC 1030.10 City Modifications; Front main entrance door has panic hardware and a dead bolt lock on it only one locking device is allowed on door, can't have dead bolt locks with panic hardware or any other locking device with panic hardware 3. Rear patio gate has a double cylinder keyed dead bolt lock, not allowed need to install a thumb style turn dead bolt lock for people to get out and not have to use a key or any special effort to open to exit to public way. |
|
| 04/15/2015 | FIRE - FINAL | Partial Approval | 1. Place 12" numbers on street side. 2. Re Inspect when special locking devices are in place. 3. Okay for TCO and stocking. |