Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2015 |
PLUMBING - INTERMEDIATE |
|
Approved |
IVRS - Inspection :* |
| 01/27/2015 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* |
| 01/27/2015 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
PLUMBING ROUGH SOIL OK TO BACKFILL |
| 01/26/2015 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 01/26/2015 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
ALL UNDERGROUND DWV FITTINGS TO BE TESTED |