Permit: T14CM07048

Parcel: 14102013D

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
12/22/2015 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
12/09/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BRIDGE TO BLDG.
10/15/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/15/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEPS TO RAMP AREA (WEST)- TRASH ENCLOSURES ( SLAB- WIVE IN PLACE OK TO POUR
10/09/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AMPHITHEATER FOOTING OK TO POUR
10/07/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING FOR MEZZANINE
08/20/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/20/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WESTSIDE RAMP & STAIRS FOOTINGS - OK TO POUR
07/13/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS AND SLAB AT NW AREA; FOOTINGS AND SLAB AT GL C/1-4; 1.25/B-C; 3.75/B-C OK TO POUR SLABS AND FOOTINGS
07/09/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
07/03/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 COLUMN FOOTINGS GL; C/1, C/6, D/6 OK TO POUR
04/30/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/29/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BUILDING #4 EXTERIOR WESTSIDE