Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/07/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :* |
| 05/07/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
INSPECTIONS COMPLETED BY J.M. AND B.B. |
| 04/17/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/15/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/07/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/07/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT NEXT LIFT PENDING SPECIAL INSPECTION |
| 04/06/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/06/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
3RD LIFT, NORTH WALL |
| 03/31/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/31/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT NEXT LIFT AT WEST, SOUTH, & EAST WALLS |
| 03/27/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/27/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT NEXT LIFT AT SOUTH & EAST WALLS |
| 03/24/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/24/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO POUR TRASH COMPACTOR SLAB |
| 03/23/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/23/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 20' LIFT @ WEST WALL |
| 03/20/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/20/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 4TH LIFT AT EAST, SOUTH, & WEST WALLS PENDING SPECIAL INSPECTION |
| 03/19/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/19/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO POUR LOADING DOCK SLAB |
| 03/18/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
3RD COURSE. ALSO, COLS |
| 03/17/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/16/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT 1ST LIFT SOUTH WALL GRID LINE B TO F, 1 TO 4 WEST WALL, F TO E ON NORTH WALL. OK TO GROUT STEM WALL AT ENTRY COLUMNS |
| 03/06/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 03/06/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK TO GROUT FIRST LIFT AT LOADING DOCK |