Permit: T14CM04464

Parcel: 14043011A


Addresses:

6951 S PARK AV

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
12/30/2014 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
11/06/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
11/05/2014 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
10/06/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
10/06/2014 PLUMBING - ROUGH, SOIL Partial Approval YARD WATER LINE TO MAIN TAP OK TO SHADE & BACK FILL
10/03/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
10/03/2014 PLUMBING - ROUGH, SOIL Partial Approval 1. GREASE RECEPTOR OK TO BACK FILL
2. WEST END ROLLING DOOR TRACK FOOTER OK TO POUR
10/02/2014 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
09/30/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/30/2014 PLUMBING - ROUGH, SOIL Partial Approval 1. 2" COPPER YARD LINE FROM BLDG TO 3" PVC MAIN APPROX 40' OK TO BACK FILL
2. 2 TRENCH DRAINS TO G,R INLET U.G OK
09/22/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/22/2014 PLUMBING - ROUGH, SOIL Partial Approval OK TO FILL BETWEEN NORTH AND WEST CLEANOUTS GREASE RECEPTORS NOT READY
09/19/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/18/2014 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
09/16/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/16/2014 PLUMBING - ROUGH, SOIL Partial Approval EAST PARIMETER FOOTER OK TO POUR
NORTH PARIMETER DWV OK TO BACK FILL
09/11/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/11/2014 PLUMBING - ROUGH, SOIL Partial Approval WEST END OF BLDG APPROVED
09/10/2014 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/10/2014 PLUMBING - ROUGH, SOIL Partial Approval EAST 3 EACH FSI WITH 3" FCO SUBMIT REDLINE FOR PLUMBING EXTERIOR OF BUILDING & ALL CHANGES
09/09/2014 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*