Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/26/2016 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* |
| 03/22/2016 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 03/16/2016 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 03/10/2016 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
BURGER KING AND MONEY STORE |
| 03/07/2016 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 02/01/2016 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* Dairy cooler drain per GP2 |
| 01/04/2016 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 12/14/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
|
| 12/11/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 11/24/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
EXPANSION AREA COMPLET |
| 11/10/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
OK TO BACKFILL 2 CONTINUOUS WASTE SYSTEMS IN NEW BLDG |
| 11/06/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
EXISTING BLDG DRAIN CONNECTION |
| 11/05/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 10/28/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
SS COLS G-L MAINS OK |
| 10/15/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 09/30/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
FRONT TOILET RMS OK |
| 09/03/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 08/24/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 06/23/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 06/23/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
STRAIGHT MAIN TO BLDG |
| 06/19/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 06/08/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 06/08/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
ALL DWV OPEN PIPES TO BE CAPPED-OFF DURING CONSTRUCTION. OK TO COVER PLUMBING AT NORTH EXPANSION. OK TO COVER WALL AND LIDS IN REAR RESTROOMS. OK TO COVER WALLS IN LOUNGE |
| 06/01/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 06/01/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
MH, STORM G OK FOR CONCRETE |
| 05/21/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 05/21/2015 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
DWV REQUIRES A TEST. PROVIDE MATERIAL SPEC |