Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T14CM03195
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2016 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 03/22/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 03/16/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 03/10/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | BURGER KING AND MONEY STORE | |
| 03/07/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 02/01/2016 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* Dairy cooler drain per GP2 | |
| 01/04/2016 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 12/14/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | ||
| 12/11/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 11/24/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | EXPANSION AREA COMPLET | |
| 11/10/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | OK TO BACKFILL 2 CONTINUOUS WASTE SYSTEMS IN NEW BLDG | |
| 11/06/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | EXISTING BLDG DRAIN CONNECTION | |
| 11/05/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/28/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | SS COLS G-L MAINS OK | |
| 10/15/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/30/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | FRONT TOILET RMS OK | |
| 09/03/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/24/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 06/23/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/23/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | STRAIGHT MAIN TO BLDG | |
| 06/19/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/08/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/08/2015 | PLUMBING - ROUGH, SOIL | Partial Approval | ALL DWV OPEN PIPES TO BE CAPPED-OFF DURING CONSTRUCTION. OK TO COVER PLUMBING AT NORTH EXPANSION. OK TO COVER WALL AND LIDS IN REAR RESTROOMS. OK TO COVER WALLS IN LOUNGE | |
| 06/01/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 06/01/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | MH, STORM G OK FOR CONCRETE | |
| 05/21/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 05/21/2015 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | DWV REQUIRES A TEST. PROVIDE MATERIAL SPEC |