Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2014 | PLUMBING - ROUGH, SOIL | Approved | ||
| 05/07/2014 | PLUMBING - ROUGH, SOIL | Partial Approval | ||
| 04/30/2014 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 04/30/2014 | PLUMBING - ROUGH, SOIL | Denied | USE REQUIRED FASTENERS ON METAL CLIPS. REMOVE ALL ROCKS FROM AROUND PIPING. CORRECT CONN TO EXISTING SEWER. REMOVE PVC. PROVIDE A TEST ON SEWER, INSTALL TRACER WIRE. REMOVE BACKWATER VALVE. EACH DRY VENT SHALL RISE VERTICALLY ABOVE FLOOD LEVEL PRIOR TO HORIZ OFFSET. SUPPORT VENTS IN WALLS & ABOVE CEILING. |