| 10/23/2014 | BUILDING - FINAL | Approved | IVRS - Inspection :* | |
| 10/21/2014 | BUILDING - FINAL | Cancelled | IVRS - RI canceled | |
| 10/21/2014 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* | |
| 10/21/2014 | BUILDING - FINAL | Partial Approval | NEED AIR BALANCE REPORT & STERLIZATION REPORT EVERYTHING ELSE OK | |
| 10/03/2014 | BUILDING - FINAL | Prior to Final Inspectn | NEED WWM RECEIPT OR CONFIRMATION FROM LORENZO TO CONTINUE | |
| 10/02/2014 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* | |
| 10/02/2014 | BUILDING - FINAL | Partial Approval | OK TO START TENANT IMPROVEMENTS PRIOR TO SHELL FINAL. PROVIDE A MINING VALVE AT LAV. FINISH ALL ELEC WK. PROVIDE A GAS LINE FOR UNIT 131 |
|
| 06/30/2014 | BUILDING - FINAL | Prior to Intermediates | PER LORENZO HERNANDEZ FROM WWM SEWER CONNECTION FEES MUST BE PAID PRIOR TO INTERMEDIATES. |