Inspection History Details
Inspection Status: Partial Approval
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T14CM01254
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Partial Approval
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 01/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | REBAR CAGES FOR 11 LIGHT POLE CAISSON FOOTINGS | |
| 11/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 11/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 5 @ LIGHT POLE CAISSON FOOTINGS- OK TO POUR | |
| 11/14/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 11/14/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 @ LIGHT POLE CAISSON FOOTINGS- GROUNDING SYSTEM IN PLACE-POURED;GL:APPROX 4.5-8 | |
| 11/06/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 11/06/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | EAST WALL FOOTINGS OF OFFICE AREA; 4 INTERIOR F4 COLUMN FOOTINGS- OK TO POUR | |
| 11/04/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 11/04/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL & COLUMN FOOTING AT GL: 6.7/G-H OK TO POUR: DETAIL #302/S3.1 | |
| 10/13/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 10/13/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STEM WALL FOOTINGS AT GL:17/C.5-G-OK TO POUR:15 COLUMN PROTECTORS AS PER DETAIL #310 & 311; PAGE S3.2-GL:2-4/B-F; OK TO POUR | |
| 09/23/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/23/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 15@ COLUMN PEDISTALS: GL: 12/B-F, 13/B-F, 14/B-F | |
| 09/19/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/19/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN SPREAD FOOTINGS AT GL: 16/B-E; COLUMN PEDISTAL FOOTINGS AT GL:9-10: OK TO POUR PROGRESS AREAS | |
| 09/17/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/17/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN SPREAD FOOTINGS GL: 5@ 12/B-F; 5 @ 13/B-F; OK TO POUR | |
| 09/16/2014 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/15/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOUNDATION FOOTING AT G/7-9 OK TO POUR | |
| 09/12/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/11/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/11/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PEDISTAL FORMS AT GL: 7, 8, 9/B-F; COLUMN FOOTINGS AT GL: 10-11/ B-F OK TO POUR PROGRESS AREA |
|
| 09/04/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/04/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOUNDATION FOOTINGS AT GL: 17/A-G. 7 PEDISTAL FOOTINGS AT GL: B/8-9 (2 @ F6-6); C/8 (1 @ F6-6); D/8-9 (2 @ F6-6A); E/8-9 (2 @ F6-6A) OK TO POUR PROGRESS AREAS | |
| 09/03/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/03/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN PEDISTALS (20) AT GL: 3/B-F; 4/B-F; 5/B-F; 6/B-F (EXCEPT FOR PEDISTAL C-6) OK TO POUR | |
| 08/27/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/27/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN AND FOUNDATION FOOTINGS: GL: A/4.5-5.5; G/4.5-5.5 OK TO POUR PROGRESS AREAS | |
| 08/26/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/26/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PEDISTALS FOR F6-6A COLUMS; GL B/2-3(2); C/(2-3)(2); E/2-3 (2); F/2-3 (2) F6-6B (2) GL: D:2-3 OK TO POUR PROGRESS AREA COLUMN FOOTINGS: 2 @ F6-6B GL: d/6-7; F6-6A @ GL:B/6 | |
| 08/25/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/25/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOUNDATION FOOTING AT GL: A/C.5-D.5; BOLLARDS IN PLACE AS PER DETAIL 010/SO.2; OK TO PROGRESS AREAS COLUMN FOOTINGS @ GL: D/5 (F6-6B); C/4/4-5 (F6-6A) SPECIAL INSPECTION 8-22-14 POURED | |
| 08/22/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/22/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS-10 COLUMN FOOTINGS (7@F6-6A, 3@F6-6B) F6 6B GL: D/3-5: F6-6A: B/4-5; C/5, E/4-5, F/4-5 OK TO POUR PROGRESS AREAS | |
| 08/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOUNDATION FOOTINGS AT GL: 1/1.4-4.5; OK TO POUR PROGRESS AREA | |
| 08/20/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/19/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS & COLUMN FOOTINGS (F3.5-3.5, F5.5) GL:G/1-4.5: INTERIORCOLUMN FOOTINGS (8@ F6-6A FOOTINGS: 2@ F6-6B FOOTINGS) GL: 2/B-F; 3/B-F : OK TO POUR PROGRESS ARES |
|
| 08/18/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/18/2014 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | EAST FOOTING AND COLUMN (9 EACH F4-4) GL: 1/D.5-F.4; D-A.5/1; OK TO POUR PROGRESS AREAS; GL 1/D-D.5 (BOLLARD AREA, TO BE POURED LATER) |