Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 06/30/2014 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 02/27/2014 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
1.Development package submitted has not been approved for plumbing. OK to continue subject to plan approval by next inspection. Approved utility plan to show private building sewer to connection with public sewer (not shown on plumbing pla) yardwater piping to each unit from the meter to the building service. Gas meter locations. Routing of private underground conduit to each unit. OK for concrete subject to approved utility plan. |
| 02/25/2014 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
1. Plan left is a model plan. For layout and rebar, and zoning I will need an approved site plan to check set backs, orientation, and plot location. |