Permit: T14CM00541

Parcel: 117200270


Addresses:

260 S CHURCH AV 01

Inspection Status: Partial Approval

Inspection History: ELECTRIC - PROGRESS

Date Description Inspector Results Comments
11/05/2014 ELECTRIC - PROGRESS Partial Approval UNDERGROUND CONDUIT TO MONUMENT - EAST OF ENTRY BREEZEWAY - IN WEST DRIVEWAY OK TO BACKFILL
10/30/2014 ELECTRIC - PROGRESS Partial Approval 1. OKTO CONCRETE CONDUIT FROM EAST CURB TO WEST DRIVEWAY.
2. RETURN TRIP TO VERIFY CONCRETE POUR. OK TO BACKFILL TRENCH.
09/24/2014 ELECTRIC - PROGRESS Not ready for Inspection
09/16/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*
09/10/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :* BREEZWAY AREA
09/09/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*PROGRESS AREA
06/03/2014 ELECTRIC - PROGRESS Partial Approval PHASE I COMPLETE FOR OCCUPANCY, HOWEVER, THE PERMANENT LIGHT FIXTURES ARE ON BACK ORDER SO ALL FIXTURES ARE TEMPORARY AND WILL BE REPLACED LATER.
05/07/2014 ELECTRIC - PROGRESS Partial Approval ROUGH WIRING AND CONDUITS OK TO COVER IN 7 LOWER LEVEL INFILL WALLS
04/24/2014 ELECTRIC - PROGRESS Partial Approval 95% OF EXPOSED 2 1/2 + 1 1/2 METAL CONDUIT. PANEL CONNECTION COMPONANTS REMAIN TO BE DONE