Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2015 | FIRE SPKLR - OH PIPING & HYDRO | Approved | not all ceiling tiles in place, but tiles with heads are in place. Will not final in contractors permit until all tiles are in place. | |
| 02/18/2015 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Insulation in place over North hall to main building. Still Need: Old auxillary drain can be removed per confirmation from the sprinkler contractor that it is not operational. Found Auxillary drain and inspectors test valve for whole system located on the far North end of the property in the laundry room. Must place uprights in the concealed combustable construction area over exterior emergency exit ( where old pipe and heads have been removed). Cleared for interior dry walling now that insulation is in place. |
|
| 02/09/2015 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Passed 200 PSI for 2 hrs. Pending: 2 uprights in concealed space (right side) at entry way need to be added where existing pipe had been removed. Fill in the concealed space with insulation, over the doorway and at the Right of the Entry. Move inspectors test valve if none other found. |