Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/02/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | 1. 200 psi test completed on 2 6" standpipe FDC lines. | |
| 11/05/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Cancelled | Called and cancelled | |
| 10/10/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 1. Partial for 2 6" FDC underground pipes. Where piping turns to a 90 degree. 2. Still need to Hydro at 200 psi for 2 hours. |
|
| 10/09/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Not ready for Inspection | Cancelled piping for FDC was not ready | |
| 10/07/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 200 PSI for 2 hours for 45 feet of 6 inch underground main for sprinkler supply, still need to flush line. Still need to test the FDC line at 200 PSI for 2 hours and flush. |