Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - KITCHEN EXH HOOD FINAL
Permit Number - T14BU00985
Inspection Description - FIRE - KITCHEN EXH HOOD FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/11/2015 | FIRE - KITCHEN EXH HOOD FINAL | Approved | APPROVED AS BUILDS SUBMITTED AND APPROVED. NOW TWO NOZZLES OVER 4 BURNER RANGE, WITH N2LP NOZZLES AT CORRECT DISTANCES. LARGER TANK HAS 20 FLOW POINTS AND 19 ARE BEING USED. |
|
05/14/2015 | FIRE - KITCHEN EXH HOOD FINAL | Cancelled | Per Carl, cancel because they are not ready for inspection. | |
05/13/2015 | FIRE - KITCHEN EXH HOOD FINAL | Denied | Correct coverage over the 4 burner grill, size on plan shows 28"x36" what is on site is 33"x26" on the approved plan shows N1LP nozzle cannot cover. Western states will be changing the coverage to using two N2LP nozzles. Need new plans showing changes for coverage and changes in the nozzle and flow points' schedule - please bubble areas that are changed. |
|
03/02/2015 | FIRE - KITCHEN EXH HOOD FINAL | Denied | 1. All electrical outlets and equipment under the hood system shall shut down when system is activated - when compliance testing was done the electrical failed to shut done. 2. Adjust nozzles to proper height and aiming point to equipment per manufacture requirements: a. 4 burner range nozzle to height and nozzle not pointed to center b. Tilting skillet - nozzles not properly installed per approved plans, nozzles need to be away from cover lid and nozzles centered to appliance per manufacture requirements. 3. More nozzles were added than what is on approved plans: a. Duct on plans state 10"x 10" when it's 23" X 23", 2 red nozzles installed not 1 b. Plenum 11' 6" plans show 1 blue nozzle on each side, 2 blue nozzles are install on both sides on site. When this was done the total nozzle points on site is now 16 the tank is 15 points therefore system is not adequate. 4. Will need as bults showing what is on site. 5. Need to check the nozzle coverage for the duct work again approved plans show 10"x10" when it's 23"x23". 6. The K-class fire extinguisher is mounted 6' above floor finish needs to be min 4" to max 5' above floor finish (to top of extinguisher). |
|
01/08/2015 | FIRE - KITCHEN EXH HOOD FINAL | Denied | 1. Western States had no way of testing flow. | |
12/24/2014 | FIRE - KITCHEN EXH HOOD FINAL | Denied | 1. Siemens unaware of testing. Need to reschedule. |