Inspection History Details
Inspection Status: Closed
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2022 | FIRE SPKLR - FINAL | Closed | CONTRACTOR DID NOT CALL IN PERMIT TO COMPLETE FINAL INSPECTION. PERMIT CLOSED WITHOUT FINAL INSPECTION. | |
| 04/09/2014 | FIRE SPKLR - FINAL | Partial Approval | Partial approval given okay use the home, to get final C of O the following is needed: 1. Fire alarm monitoring system install for tamper and water flow 2. Added sprinkler coverage under the patio 3. Need as bults for changes 4. Need a breaker lock on the breaker for the fire alarm bell |
|
| 03/24/2014 | FIRE SPKLR - FINAL | Denied | 1. Cannot use a Globe valve for the main shut off on the riser. 2. System will need to be monitored as this systems has it's own water supply line. Both tamper (when installed) and flow switch. You will need a separate plan and permit for this work. 3. Need to do a flow and drain test for finals. |