Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2014 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 03/27/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/27/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1. SITE WALL COMPLETE PER DETAIL 37 2. EXTERIOR WALL PER DETAIL 111/S3.0. (?) TO BE EPOXY INSTEAD OF AB GRID LINE 5 BETWEEN B & C 3. EXCEPT WATERPROOFING @ PLANTER PER DETAIL LOG |
|
| 03/20/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/20/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1ST LIFT AT SOUTH SITE WALL OK | |
| 03/18/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/12/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/10/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/06/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/06/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OFFICE & RESTROOM AREA NORTH AND NORTHEAST OK AT TOP-OUT. SOUTH AND SOUTHEAST OK AT 24' | |
| 03/04/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 03/04/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | STEM WALL AT NORTH SITE WALL OK | |
| 02/28/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/28/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 5TH LIFT AT OFFICE, RESTROOMS, & OPS OK | |
| 02/25/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/20/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/20/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1. 3RD LIFT AT OUTSIDE WALL OF OFFICE & RESTROOM AREA OK TO GROUT 2. 1ST LIFT ALONG SOUTH WALL OF SHOP AREA OK TO GROUT |
|
| 02/18/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/18/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 3RD LIFT OK AT OPERATIONS, OFFICE INSIDE WALLS, AND RESTROOM AREA | |
| 02/11/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 02/11/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 2ND LIFT AT OPERATIONS, RESTROOMS, & OFFICES OK | |
| 02/05/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1ST LIFT AT OFFICE AND OPERATIONS OK TO GROUT | |
| 01/16/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 01/16/2014 | REINFORCED MASONRY PRE-GROUT | Partial Approval | STEM WALLS AT BLDG (MAIN) OK |