Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 03/12/2014 |
BUILDING PRE-SLAB |
|
Approved |
IVRS - Inspection :* |
| 01/27/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
IVRS - Inspection :* |
| 01/27/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
MATTING ON SHOP INTERIOR OK |
| 01/23/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
IVRS - Inspection :* |
| 01/23/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
NORTH & SOUTH PERIMETER STRIPS OK |
| 01/22/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
IVRS - Inspection :* |
| 01/22/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
STRIPS ALONG C.L. 2 & 4 OK TO POUR |
| 01/21/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
IVRS - Inspection :* |
| 01/21/2014 |
BUILDING PRE-SLAB |
|
Partial Approval |
NORTH & CENTER SECTIONS AT SHOP COMPACTION OK - OK TO INSTALL REBAR |