Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Approval
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/28/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CMU WALLS AT 8' - 12' GL: A-B; .5-11; SOUTHWEST WALL & COLUMNS AT 4' - 8'; OK TO GROUT |
| 03/18/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :* |
| 03/17/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
IVRS - AP canceled |
| 03/17/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
NORTH & EAST WALLS TOPPED OUT AT 20'8"; SOUTH WALL AT 20'8"; SE PIER AT 24'8"; OK TO GROUT PROGRESS AREAS |
| 03/13/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
IVRS - AP canceled |
| 03/10/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
IVRS - AP canceled |
| 03/07/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
2 @ COLUMNS SW CORNER AT 4'; 8' - OK TO GROUT PROGRESS AREAS |
| 03/06/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
IVRS - AP canceled |
| 02/26/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
IVRS - AP canceled |
| 02/25/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CMU WALLS AT 12'-16'8" - EAST WALL & NORTH WALL; SE CORNER AT 8'-12' - OK TO GROUT PROGRESS AREAS WHEN LEDGER BOLTS ARE IN PLACE. |
| 02/21/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 02/21/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
CMU WALLS AT 8'-12' GL: NORTH WALL; EAST WALL; SE CORNER AT 4'-8'; SE COLUMN AT 4'-8'; NOTE MASONRY PROGRESS AT 0'-8' ON WALLS SPECIAL INSPECTED, GROUTED. SITE WALLS & TRASH ENCLOSURE TOPPED-OUT & GROUTED |
| 02/14/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 02/14/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
SITE/RETAINING WALL AT 24"-48" OK TO GROUT 1ST LIFT |
| 01/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 01/23/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
BUILDING STEM WALL GROUTED - SPECIAL INSPECTED |