Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T13CM06289

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
03/24/2015 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
02/18/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 6 @ SCALE FOOTINGS AS PER DETAIL #122, PAGE 2S3.1 - BOLLARDS INCLUDED
01/23/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/22/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LIGHT POLE BASES
01/14/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*COLUMN FOOTINGS AT SCALE BLDG (2)
01/06/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*STEM WALL FOOTINGS (APPROZ 100') EAST SIDE OF SCALE BLDG SCALE WALL FOOTINGS 6 AS PER DETAILS #122,123 PAGE 352.1 OK TO POUR FOOTINGS
12/30/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/30/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SCALE HOUSE WALLS AT 8'-12' - OK TO GROUT
12/17/2014 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
12/17/2014 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELED - RAINED OUT
12/12/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/12/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS FOR TRASH ENCLOSURE; GENERATOR ENCLOSURE (2)
12/10/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/10/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS (2) AS PER PLANS - OK TO POUR
10/30/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/20/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/20/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINOUS FOOTINGS FOR SCALE HOUSE PAVILION & COLUMN FOOTINGS AT GL:1-3/A-B- OK TO POUR PROGRESS AREAS