Inspection Status: Approved

Inspection History: ELECTRIC - PROGRESS

Date Description Inspector Results Comments
08/15/2014 ELECTRIC - PROGRESS Approved IVRS - Inspection :*
07/21/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*
07/21/2014 ELECTRIC - PROGRESS Partial Approval PANEL "MDP" GROUND BAR OK TO ENERGIZE-TO BE WORKED OUT BONDING TO GAS & WATER LINES COMMERCIAL SITE OK TO ENERGIZE "MDP" PANEL
06/13/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*
05/22/2014 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*
05/22/2014 ELECTRIC - PROGRESS Partial Approval ELECTRIC INTERMEDIATE WALLS - WEST PORTION OF BUILDING