Permit: T13CM05500

Parcel: 13014447A


Addresses:

1305 S ALVERNON WY


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T13CM05500

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
07/30/2014 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
06/06/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
06/06/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 9 LIGHT POLE BASES OK TO POUR
05/22/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
05/22/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 6 CANOPY - DRIVE-THRU COLUMN FOOTINGS, TRASH ENCLOSURE FOOTINGS - OK TO POUR PROGRESS
04/03/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/03/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 @ F5 COLUMN FOOTINGS AS PER DETAIL 11/S2 - OK TO POUR COLUMNS
03/14/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/14/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 @ F-5 FOOTINGS AT GL : 11/D-F OK TO POUR FOOTING
03/03/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/03/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 F5 COLUMN FOOTINGS; GL: 12/D-F - OK TO POUR FOOTINGS
02/14/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/13/2014 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS COLUMN FOOTINGS F1,2,3,4,5,6,7,
OK TO POUR PROGRESS AREAS
AS PER DETAILS 1,2,3 PAGE S1.2