Permit: T13CM05038

Parcel: 11904442A


Addresses:

3508 S 8TH AV #01

Inspection Status: Partial Approval

Inspection History: ELECTRIC - PROGRESS

Date Description Inspector Results Comments
03/18/2022 ELECTRIC - PROGRESS Partial Approval PARTIAL, INSPECTION FOR LOT 22 & 30 APPROVED AND OK TO OCCUPY.
02/22/2020 ELECTRIC - PROGRESS Not ready for Inspection Connectors shall be used at box connections,
holes in boxes shall be plugged,
02/19/2019 ELECTRIC - PROGRESS Partial Approval unit 1 OK and made safe electrically inside and out.
11/15/2018 ELECTRIC - PROGRESS Partial Approval 5 poles set only
Units 32,33,24,29 & 26
10/03/2018 ELECTRIC - PROGRESS Not ready for Inspection
10/01/2018 ELECTRIC - PROGRESS Not ready for Inspection CANCELLED
09/27/2018 ELECTRIC - PROGRESS Not ready for Inspection CANCELLED
03/27/2018 ELECTRIC - PROGRESS Partial Approval #2 ok
03/21/2018 ELECTRIC - PROGRESS Partial Approval unit 2 protect wiring in closet
03/07/2018 ELECTRIC - PROGRESS Denied unit 2 install nail plates on conductors less than 1 1/4" from face of framing members
02/02/2018 ELECTRIC - PROGRESS Not ready for Inspection Inspection requested for units 1 and 2.
U#1 has gas pipe work in progress within a Recreational Vehicle.
Gas piping is also being reworked on the Master Meter system. This system is off and is one of three systems, only one Master Meter system is live.
U#2 has electrical re-work in progress and is also a RV.

I do not know the scope of the work to be inspected on this site, many other inspectors have been here before.
12/08/2017 ELECTRIC - PROGRESS Partial Approval unit 5 ok to occupy
10/06/2017 ELECTRIC - PROGRESS Partial Approval unit 16 ok to occupy
08/01/2017 ELECTRIC - PROGRESS Partial Approval unit 3 ok
09/20/2016 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*
09/20/2016 ELECTRIC - PROGRESS Partial Approval #4 ok to occupy
04/19/2016 ELECTRIC - PROGRESS Partial Approval INSPECTION TODAY WAS REQUESTED BY THE PARK OWNER, GLENN HARMON. THIS WAS REQUESTED IN RESPONSE TO CODE ENFORCEMENTS LATEST ADDITION TO VIOLATIONS T16DV01033, ON 3/16/16, CONCERNING THE CONDITION OF THE EXISTING SERVICE EQUIPMENT. THE INSPECTOR WILL CONTACT THE CONTRACTOR OF RECORD AFTER CONSULTING WITH THE BUILDING OFFICIAL.
03/03/2016 ELECTRIC - PROGRESS Partial Approval IVRS - Inspection :*