Inspection Status: Partial Approval
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2022 | BUILDING - PROGRESS | Partial Approval | PARTIAL, INSPECTION FOR LOT 22 & 30 APPROVED AND OK TO OCCUPY. | |
| 02/26/2018 | BUILDING - PROGRESS | Not ready for Inspection | The City of Tucson will inspect new work done in recreational vehicles per Bruce Stevens City of Tucson Construction Supervisor. | |
| 02/02/2018 | BUILDING - PROGRESS | Not ready for Inspection | Inspection requested for units 1 and 2. U#1 has gas pipe work in progress within a Recreational Vehicle. Gas piping is also being reworked on the Master Meter system. This system is off and is one of three systems, only one Master Meter system is live. U#2 has electrical re-work in progress and is also a RV. I do not know the scope of the work to be inspected on this site, many other inspectors have been to this site prior, I was not shown any plans. |