Inspection Status: Denied
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/08/2014 |
ENGINEERING - FINAL |
|
Denied |
WALKED SITE WITH DAVE AND GC .WENT OVER GRADING PLANS AND THING THAT NEED TO BE DONE. |
| 05/08/2014 |
ENGINEERING - FINAL |
|
Approved |
THERE ARE STILL PLAN REVISIONS AND MINOR CORRECTIONS TO BE MADE BUT THEY WILL BE DONE ON DP ACTIVITY |
| 05/07/2014 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
|
| 04/10/2014 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
|
| 02/27/2014 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
MET WITH RON ON THIS SITE AND LOOKED AT THE WORK THAT HAD BEEN COMPLETED. MOST OF THE WORK THAT WAS NOTED ON THE PLANS HAD NOT BEEN CONSTRUCTED AS SHOWN AND APPROVED. CONTRACTORS PERSONEL IS NOT ONSITE AT THIS TIME, RON WILL GIVE THEM THE INFORMATION ABOUT WHAT IS REQUIRED PRIOR TO A FULL APPROVAL OF THE SITE FORM THE COMBO PERMIT OR THE DEVELOPMENT PACKAGE. PICTURES WERE TAKEN DURING THIS SITE VISIT THEN I DISCUSSED THE SITE WITH DAVID RIVERA, HE SAYS THERE WILL BE NO DSMR'S ISSUED FOR THE LACK OF CORRECT WORK. |
| 02/21/2014 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
PROVIDE APPROVED PLANS FOR ALL ACTIVITYS FOR 102 NALVERNON WY. |