Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 10/10/2013 |
PLUMBING - PROGRESS |
|
Approved |
IVRS - Inspection :* |
| 10/04/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 10/04/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
PIPE EA COMPARTMENT OF 3 COUP SINK SEPARATELY TO FS. SUPPORT INDIRECT PIPING AS NEEDED. INSTALL RPBP AT STORI WX W/ TEST. PRIME CEMENT AND SUPPORT ALL PVC DRAINS W/ APPROVED SUPPORTS. LAVITORY MIXING VALVES, ADD SUPPORTS. ACCESS TO HW. |
| 09/05/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 09/05/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
FLORAL OK. INSTALL DOME STRAINER & WATER TEST SINK. ADD SUPPORT ON OVERHEAD VENT. WILL REINSPECT. |