Inspection History Details
Inspection Status: Partial Approval
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/07/2013 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
| 05/07/2013 | PLUMBING - GAS PRESSURE TEST | Partial Approval | CORRECT DRIPPING RELIEF VALVE COMPLETE NOTED ITEMS OK FOR GAS RECALL FOR FINAL INSP DO INSP AFTER NOON |
|
| 05/03/2013 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 05/03/2013 | PLUMBING - GAS PRESSURE TEST | Denied | PROVIDE ACCESS TO FURNACE & DETECTOR. CARBON MONOXIDE DECTOR REQUIRED. EXTEND B VENT TERMINATIONS THAT ARE WITHIN 10' OF COOLER. B VENT REQUIRES MIN 1" CLEARANCE. NEW GAS FLUX REQUIRED AT WH. SOURCE FLASHINGS W/ GALVANIZED FASTENERS SEAL FLASHINGS PROVIDE ELECTRICAL BONDING PROVIDE A FULL SIZE TOE 1X3/4X3/4 AT SPLIT |