Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/03/2015 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* |
| 05/12/2014 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. At interceptor- inlet, outlet, vent, and connecting piping OK to cover. At mat wash- to interceptor OK to cover. |
| 05/09/2014 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. Interceptor being set. |
| 10/23/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. Solvent weld storm drain complete underground OK. Subject to water test. |
| 10/23/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. Underground storm water drains water test OK. OK to cover. |
| 10/22/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 10/17/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 10/17/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PARTIALLY APPROVED - OK TO COVER UP INTERIOR GREASE WAY (UNDER SLAB) |
| 10/16/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. East side PVC DWV under test. Electric conduit under slab. |
| 10/14/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. 8" and 6" rainwater leader next to column 7.1 and next to grid line "C" subject to a test at a later date. |
| 10/08/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. SouthEast quadrant PVC DWV under slab OK to cover. |
| 10/07/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. West of column line "6" PVC DWV under slab OK. |
| 10/04/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 09/30/2013 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
|