Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T13CM02593
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2014 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
| 12/10/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1, Infill at column pads OK. | |
| 11/13/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Screen wall West side. | |
| 11/08/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Canopy column pads (16) OK to cover. | |
| 09/30/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Column pads "D" 7.1, "F" 8.2, "E" 9.1 | |
| 09/27/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Gridline "A" 1-9 column pads. AK Duct main OK to cover (blue duct) | |
| 09/26/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Footings "D"5.1 "C"-7, "C"-8, "C"-9. Grade beam grid line "B" 7-9 Gridline "10" A-C | |
| 09/24/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Column pads 3.1-"D", C-4, 4.1 G-5, 5-C. Grid line six grade beam. | |
| 09/24/2013 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 09/23/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. At elevator, masonry topped out, one section recesses for box access. Grade beams at column #06. and "B" 4.5 to "B" 6.75. | |
| 09/20/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Grade Beam at grid 2.1. Double footing (F-6) at column 1-C. Double footing at (F-7) at grid 1.1D. 2-F-8 footings ffor stairwell. | |
| 09/19/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Columns 6.1-8.1 grade beam at grid line "B" Two columns at elevator set. UFER at columns 6.1-8.1 | |
| 09/17/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Grade beams at Grid "H" 5.1 - 3.1 Grade beam at 4.1 OK for concrete. | |
| 09/16/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. At elevator pit: Columns F-1 and F-2 footings installed per details 107, 108, on S3.0. Sump pit installed per detail 109 on S3.0 | |
| 09/12/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1. Wall at grid line "B" OK for concrete. Wall at gridline "1" OK for concrete. | |
| 09/06/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* |