Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T13CM02372
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2013 | SITE - SEWER | Approved | ||
08/27/2013 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
08/08/2013 | SITE - SEWER | Partial Approval | 1. Testing of branch laterals required by engineer. | |
08/06/2013 | SITE - SEWER | Partial Approval | 1. Begin mirror and mandrill, also low pressure air test. | |
06/10/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/31/2013 | SITE - SEWER | Partial Approval | 1. Poured manhole bases #3, and #5. Plumber to use hubsets at sewer connections. Private sewer not connected to public sewer | |
05/24/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/23/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/21/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/21/2013 | SITE - SEWER | Partial Approval | FROM C.O. 7 TO 10 AND 7 TO 11 | |
05/20/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/20/2013 | SITE - SEWER | Partial Approval | C.O. 7 THRU 8 | |
05/17/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/17/2013 | SITE - SEWER | Partial Approval | MANHOLE #4 TO C.O. #7 | |
05/16/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/16/2013 | SITE - SEWER | Partial Approval | MANHOLE BASE 1 & 2 SEWER FROM 3/4 |
|
05/15/2013 | SITE - SEWER | Partial Approval | L.O 6 TO MANHOLE | |
05/14/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/10/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/09/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/08/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/07/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/07/2013 | SITE - SEWER | Partial Approval | MANHOLE 2 THRU CLEAN OUT #3 | |
05/03/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/03/2013 | SITE - SEWER | Partial Approval | SEWER MANHOLE 2 TO 3 | |
05/02/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/02/2013 | SITE - SEWER | Partial Approval | SEWER FROM MH1-MH2 | |
05/01/2013 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
05/01/2013 | SITE - SEWER | Partial Approval | DIGGING FROM NEW MH #1 TO NEW MK #2 AND FROM #2 TO NEW MANHOLE #3- READY FOR PIPE DON'T FORGET GREEN TRACER. | |
04/30/2013 | SITE - SEWER | Partial Approval | 1. Digging begins! Located 8" SDR-35 |