Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
| Date |
Description |
Inspector |
Results |
Comments |
| 08/14/2013 |
SHEET ROCK NAILING |
|
Approved |
|
| 07/29/2013 |
SHEET ROCK NAILING |
|
Partial Approval |
1. I am unable to approve the plumbing until you have a revised approved plan. Note: Point of vent may not be below the trap weir. |
| 07/26/2013 |
SHEET ROCK NAILING |
|
Partial Approval |
1. Overhead at Mezzanine OK for rock. OK to cover old mechanical drops. |