Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 08/27/2017 |
PLUMBING - PROGRESS |
|
Approved |
|
| 06/27/2013 |
PLUMBING - PROGRESS |
|
Not ready for Inspection |
1. Pumped discharge not installed per plan. New unapproved plan shows pouring a manhole over an existing six inch clay sewer, which happens to be in an easement making it a public manhole. Comply with PCWWM. Private sewer from apartment buildings #01 and #02 and connected to lift station, tested OK. |
| 06/26/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Spark test lift station. |
| 06/25/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. OK to backfill around lift station and grinder. |
| 06/21/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 06/20/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Pouring base under 6" existing clay sewer lift station installed. |
| 06/19/2013 |
PLUMBING - PROGRESS |
|
Not ready for Inspection |
|