Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
Permit Number - T13CM00975
Inspection Description - FIRE SPKLR - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/13/2014 | FIRE SPKLR - FINAL | Approved | ||
10/16/2013 | FIRE SPKLR - FINAL | Denied | 1. Analytical Lab shower need sprinkler coverage X2 2. Chem storage room correct coverage 8' 6" off wall 3. Mineralogy - high grade room correct sprinkler coverage 8' 6" off wall 4. Mineralogy - Mid grade room correct sprinkler coverage 8' 6" off wall 5. In corridor (on plans S-46 next to personnel space, submittal office, supervisor office) correct sprinkler coverage 6. Mineralogy north correct sprinkler coverage in shower 7. East corridor area C (by Qemscam rm, Util Chase rm, XRD Lab rm) correct sprinkler coverage heads 20' feet apart 8. Hydro test all new piping installed for the dry system for 2 hours at 200 PSI. |
|
09/13/2013 | FIRE SPKLR - FINAL | Partial Approval | 1. ok to occupy phase one only. 2. sprinkler placemet is ok in phase one water flow was tested and passed tampers not online although they are chained open. 3. move handicap sign away from fdc 4. emergency lights tested and passed in phase one |