Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
Permit Number - T13CM00547
Inspection Description - ELECTRIC - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2014 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 07/17/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/27/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/24/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/23/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | TORQUE TEST AT PENTHOUSE | |
| 06/18/2014 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 05/07/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 05/07/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | PANELS 13P, 13PL | |
| 05/01/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/30/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/30/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | PANELS 25BH, 25BP, XFMR25B | |
| 04/29/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | PANELS ON UNITS 12TH & 13TH FLOORS | |
| 04/24/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/23/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 9P, 10EL, 12EL LIGHTING CORRIDOR | |
| 04/22/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/22/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | CORRIDOR LIGHTING PANELS. 2P-3P. H1 TRANSFORMER | |
| 04/21/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/21/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | ATS SWEN, SWSB TRANSFORMERS. PANEL 2H, 2EL, 3PA, 4EL, 6P, & 7EL OK | |
| 04/15/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/15/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 11TH FLOOR PANELS ON UNITS | |
| 04/10/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/10/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | STAIRWELL #2 11TH-13TH | |
| 04/08/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/08/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 10TH FLOOR PANEL ON UNITS | |
| 04/04/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 04/03/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 9TH FLOOR PANELS | |
| 04/01/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/31/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 8TH FLOOR PANELS IN UNITS | |
| 03/26/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/25/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 12TH FLOOR UNITS AND CORRIDOR | |
| 03/24/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/21/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 13TH FLOOR UNITS OK. 7TH FLOOR PANELS ON UNITS | |
| 03/19/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/13/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/13/2014 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/13/2014 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | 12TH FLOOR UNITS INCOMPLETE | |
| 03/12/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | PANEL IN UNITS 2 THRU 5 | |
| 03/05/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/04/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | 13TH CORRIDOR & DEMISING WALLS. 1ST FLOOR CORRIDOR WALLS | |
| 02/21/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 02/20/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | ELEC CORE AND FRAMING ON ROOF. STAIRS 1 & 2, FLOORS 2 THRU 6 | |
| 02/18/2014 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 12/20/2013 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 11/21/2013 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 11/20/2013 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 11/20/2013 | ELECTRIC - INTERMEDIATE | Partial Approval | LEVEL 2 EXCLUDES ROOM #201 | |
| 11/19/2013 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* |