Permit: T13BU01428

Parcel: 13303301E


Addresses:

9971 E SPEEDWAY BL


Inspection Status: Partial Approval

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Permit Number - T13BU01428

Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO

Inspection Status - Partial Approval

Date Description Inspector Results Comments
05/19/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for Building 22 UG placement, wired and plactic wrap -0KAY to bury
2. Still needs 200 psi for 2 hour test
01/10/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for 200 psi hydro test on buildings 17 & 18.
01/09/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for 200 psi hydro test on buildings 19, 20, & 21.
01/08/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for 200 psi hydro test on buildings 14, 15, & 16.
01/06/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Placement and mega-lugged with plastic wrap and tracer wire in place okay to bury, for buildings 17 and 18. Still need to hydro at 200 psi for two hours.
01/03/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for UG placement for buildings 20 & 21.
2. Okay to backfill.
01/02/2014 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Partial for UG placement for buildings 14,15,16 & 19.
2. Okay to backfill.