Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | ||
| 04/01/2014 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | Tested both undergrounds failed to hold. | |
| 06/12/2013 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | did 200 psi on fire riser pipe stub. Ifc 2012 section 914.3.1.2 water supply to required fire pumps. required fire pumps shall be supplied by connections to a minimum of two water mains located in different streets. seperate supply piping shall be provided between each connection to water main and the pumps each connectionand the supply piping between the connections and the pumps shall be sized to supply the flow and pressure required for pumps to operate. handout was given to contractor with this code and the exceptions. |