Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2013 | FIRE SPKLR - OH PIPING & HYDRO | Approved | ||
| 11/18/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 200 psi for 2 hours test on both stairwells 1 & 2 standpipes only - PASSED | |
| 10/17/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 7th floor OH 200 psi for 2 hours and placement APPROVED | |
| 09/27/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 6th floor ohpt passed. need to check placement in stairwell on final #2 |
|
| 07/03/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for 200psi on 5th floor. | |
| 06/05/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. lower level 200 psi passed. stand pipes to be tested later date. 2. fourth floor 200 psi passed . |
|
| 06/03/2013 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | Basement failed leaking pipe 200 PSI testing and overhead placement approved in the following areas: 1st floor - still need to check the trash shoot area (northwest corner) 2nd floor - Need to check ramp from 2nd floor to outside road piping not made up due roll down doors going in, also check south side by 2nd stairwell head block by pillar. 3rd floor - check south side by 2nd stairwell head block by pillar. |