Permit: T12PL00102

Parcel: 12911001K


Addresses:

1000 E 22ND ST


Inspection Status: Approved

Inspection History: SITE - SEWER

Permit Number - T12PL00102

Inspection Description - SITE - SEWER

Inspection Status - Approved

Date Description Inspector Results Comments
09/19/2012 SITE - SEWER Approved CONTRACTOR WAS UNABLE TO LIVE SERVER CONNECTION UNTIL AFTER PCDEQ AUTH TO DISCHARGE. ACTIVITY REOPENED TU MAKE THIS INSPECTION INCLUDE ASI DRAWING CONTRACT DOCUMENT
07/27/2012 SITE - SEWER Partial Approval 1. Vacuum testing of manholes.
07/24/2012 SITE - SEWER Partial Approval 1. Continue low pressure air test on Private Sewer System.
07/23/2012 SITE - SEWER Partial Approval 1. Mandrill pull and low pressure air test today.
07/19/2012 SITE - SEWER Partial Approval 1. Sewer backfilled. Ready for testing.
07/18/2012 SITE - SEWER Partial Approval
07/16/2012 SITE - SEWER Partial Approval 1. Stacking manholes #6, #7, #8, #9, #12, 2. Continuing HCSs
07/16/2012 SITE - SEWER Not ready for Inspection 1. Site conditions wet. Contractor not on site.
07/13/2012 SITE - SEWER Partial Approval 1. Continuing backfill and HCS connections.
07/12/2012 SITE - SEWER Partial Approval 1. Poured manhole #9 2. Continuing HCS connections and backfill.
07/11/2012 SITE - SEWER Partial Approval 1. Manholes #3, #4, #5, #17 stacked. 2. Poured #6, #7, #8, and #12 bases poured. 3. Continuing on back fill and HCS connections.
07/06/2012 SITE - SEWER Partial Approval IVRS - Inspection :*
07/05/2012 SITE - SEWER Partial Approval 1. From manhole #7 to manhole #8, and from manhole #8 to manhole #9. OK to cover subject to verification of grade, and test at a later date. 2. Continuing HCS's on the West side. 3. Poured manholes #3,#4, #5, and #17.
07/05/2012 SITE - SEWER Not ready for Inspection 1. Due to wt site conditions, no equipment moving today.
07/02/2012 SITE - SEWER Partial Approval 1. 8" SDR 35 from manhole #6 to #7 OK 2. 8" SDR 35 from manhole #7 to #12 OK 3. 8" SDR 35 from manhole #7 to #9 OK 4. OK to cover subject to verification of grade and testing at a later date. 5. Installing HCS's on the West side.
06/29/2012 SITE - SEWER Partial Approval 1. 8" SDR 35 from manhole #5 to #17 OK 8" SDR 35 from manhole #5 to #6 OK. 8" SDR 35 from manhole #6 to #7 OK 8" SDR 35 from manhole #7 to #12 OK. OK to cover subject to test and verification of grade at a later date. Don't forget to call in when the bases are being set, and manholes stacked.
06/28/2012 SITE - SEWER Partial Approval 1. From manhole #3 to #4, and from manhole #4 to #5. Also all HCS branches.
06/27/2012 SITE - SEWER Partial Approval IVRS - Inspection :*
8" SDR 35 FROM MH #15 TO #14 AMD FROM #14 TO # 13 PRIVATE MANHOLE#1 MANHOLE STALKED BRANCHES ? 1 AND 2 AND 2 AND 3
06/25/2012 SITE - SEWER Partial Approval 1. 8" SDR-35 from manhole #15 to #14, and from #14 to #13. 2. Private manhole #1 stacked. 3. Branches between #1 and #2 - #2 and #3 installed.
06/22/2012 SITE - SEWER Partial Approval 1. Eight inch SDR-35 from public manhole #9, to private manhole #13 and from manhole thirteen to manhole fourteen, OK to cover, subject to test and verification of grade, at a later date. 2. 8" SDR-35 installed from manhole #3 to manhole #11, with branch tees installed OK.
06/21/2012 SITE - SEWER Partial Approval 1. 8 inch SDR-35 with tracer wire installed between MH #2 and MH #3 OK 2. 8 inch SDR-35 extended upstream from MH #3 to MH #4 OK 3. Bases poured manholes # 1, 2, 3. 4. Base poured manhole #15. 5. Branch laterals installed between #15 and #16.
06/20/2012 SITE - SEWER Partial Approval 1. Branch fittings installed between public manhole #2 and prtivate manhole # 1. Branch fittings installed between manhole # 1 and manhole # 2. 2. Public manhole # 9 upstream eight inch SDR 35 with branch fittings installed to manhole # 15, and to # 16.
06/19/2012 SITE - SEWER Partial Approval 1. Public manhole number two, to private manhole number one, OK to cover. 2. Public manhole number nine upstream, eight inch SDR 35 installed to manhole number fifteen, OK to cover. Manhole fifteen to manhole sixteen OK to cover subject to verification of grade and test at a later date. 3. Standard detail 401 PCWWM is for tapping into a live main (public) Private sewer installed per 2006 UPC requires changes of direction to be through approved drainage fittings. 706.1 2006 UPC. Tapping of eight inch private sewer main for the purpose of making branch intervals, will require a Petition of Appeal from the building official.
06/15/2012 SITE - SEWER Partial Approval 1. Starting at Public Manhole #2, upstream toward Private Manhole #1. Installed eight inch SDR 35. Subject to verification of grade and test at a later date.