| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/11/2012 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 01/10/2012 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) REMOVE ALL TAPE FROM VENT CONNECTORS 2) PROVIDE PROPERLY INSTALLED JOINTS 3) FASTEN WITH SCREWS 4) CONTRACTOR REQUIRED |
|
| 01/05/2012 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 01/04/2012 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1) A 10 PSI TEST IS REQUIRED 2) PROVIDE CORRECT VENTING OF FURNACE AND WATER HEATER 3) CHECK WATER HEATER RELIEF VAVLE FOR PROPER OPERATION 4) PROVIDE ELECTRICAL BONDING |