Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - TEMPORARY SERVICE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2012 | ELECTRIC - TEMPORARY SERVICE | Approved | IVRS - Inspection :* | |
| 01/20/2012 | ELECTRIC - TEMPORARY SERVICE | Partial Approval | IVRS - Inspection :* 1) CONTRACTOR (FAULK) WILL REQUEST FIELD EVALUATION INSPECTION FROM MCGETRICK ENGINEERING FOR REUSING EXISTING SWITCH GEAR AFTER FIRE 2) NEW 1200 AMP 600V MAIN BREAKER TO BE FIELD TESTED (GFI) SYSTEM OPERABLE PER MANUFACTURE 230.95 NEC 3) EXISTING SES IN RECONNECTED VIA GENERATOR AT THIS TIME 4) OK ?-4" PVC 1-1 1/4" FOR SECONDARYS AT X-FORMER TO 5' OF BLDG 5) SPOKE TO MATEO SERVICE MANAGER FOR THIS GE FACILITY HE AGREED TO HAVE A GE INSPECTION PERFORM FIELD EVALUATION FOR EXIST. SES EQUIPMENT |
|
| 01/13/2012 | ELECTRIC - TEMPORARY SERVICE | Partial Approval | IVRS - Inspection :* 1) OK TEMP GENERATORS AS CONNECTED 2) CALL FOR FINAL AFTER GENERATORS REMOVED |
|
| 01/11/2012 | ELECTRIC - TEMPORARY SERVICE | Denied | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* 1) CABLES/OVER CURRENT TO MEET CODE/PLANS 2) CKT BREAKERS ON GENERATORS TO B16 FOR CABLE SIZE 310.15 NEC |