| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/26/2015 | ENGINEERING - FINAL | Approved | ||
| 06/25/2015 | ENGINEERING - FINAL | Approved | ||
| 06/24/2015 | ENGINEERING - FINAL | Partial Approval | 1) FINAL GRADING PERMIT# DP12-0226. 2) PROVIDE AN AS-BUILT FOR INSPECTION 3) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD 4) PROVIDE COPIES OF ELEVATION CERT |
|
| 03/27/2015 | ENGINEERING - FINAL | Continued | COMPLETE SITE WORK, CALL FOR RE-INSPECTION | |
| 02/18/2015 | ENGINEERING - FINAL | Denied | PRIOR TO FINAL APPROVAL: 1) COMPLETE SITE/GRADING AND LANDSCAPING PER YOUR APPROVED PLANS 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD AND LANDSCAPE ARCHITECT STATING THAT SITE/GRADING , LANDSCAPING WAS COMPLETED PER YOUR PLAN 3) PROVIDE AS-BUILT DRAWING PER YOUR PLAN 4) SATISFY PERMIT # DP12-0226 5) PHYSICALLY SEPARATE AND COMPLETE SITE GRADING AND LADSCAPING. 6) CONDITIONS FOR PERMIT#DP12-0226 Additonal conditons added per Revision Nov2014: 1) Submit Elevation certificates for both buildings including Finished Construction and Building Under Construction. 2) Assure elevator shaft is in compliance with Floodplain Ordinance (depending on outcome of El Certs). 3) Remaining fees shall be paid prior to final approvals (Floodplain Use Permit fees and any other fees). 4) When ready for final inspections, submit Substantial Completion documentation from EOR, with as-builts, showing as-built spot elevations in the existing and newly constructed sidewalk areas at intersection, adjacent to new building structures, and within accessibility stalls and routes to clarify that maximum slopes have not been exceeded. |
|
| 02/13/2015 | ENGINEERING - FINAL | Denied | PROVIDE DOCUMENTATION SHOWING HOW CONSTRUCTION IS GOING TO BE HANDLED AND SEPERATED FROM THE LIVE TRAFFIC IN THE SOUTH PARKING LOT. ALL LANDSCAPING HAS NOT BEEN COMPLETED IN THE PARKING AREA LOCATED AT THE SOUTHWEST CORNER AND IS REQUIRED. PROVIDE AS-BUILT DRAWINGS FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE ALONG WITH A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD. TEMPORAR C OF O IS NOT TO BE CONSIDERED AT THIS TIME UNTIL ALL WORK CAN BE SEPERATED FROM ALL AREAS WHERE CUSTOMERS WILL HAVE ACCESS TOO. |