| 06/24/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :* |
| 06/11/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 06/10/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
PROGRESS ON SITE WALL |
| 06/05/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 06/04/2015 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
STEM OK |
| 11/19/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 11/18/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 11/18/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
STEM AT SOUTH SIDE |
| 11/13/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 11/13/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
PROGRESS ON SITE WALL |
| 11/07/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 11/07/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
TRASH ENCLOSER 2ND LIFT, NE STEM WALL BOARD BEAM |
| 04/25/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/25/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
TOP-OUT ADMIN BUILDING |
| 04/21/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Four to eight feet at S.E. exterior wall. |
| 04/17/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Exterior wall continues. |
| 04/16/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. North East exterior wallto fourteen feet OK. OK to grout. |
| 04/15/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* |
| 04/15/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
GL QT(?)/19-20 1ST LIFT; C/10-14 3RD LIFT |
| 04/09/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Masonry topped out at North and South ends of the West exterior wall. First four feet of the NE exterior wall grouted. |
| 04/09/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. four feet to eight feet at North East exterior wall OK. |
| 04/04/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Twelvve to sixteen feet at West wall. Up to four feet at North-East wall. |
| 04/02/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Exterior wall continued. |
| 03/31/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. eight to twelve feet at exterior wall. |
| 03/25/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Four to eight feet at exterior West wall. |
| 03/20/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Exterior wall West side first lift OK. |
| 03/11/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Twenty to twentyfour feet OK at elevator shaft. |
| 03/11/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Last lift and top cap at elevator shaft. |
| 03/10/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Sixteen to twenty feet at elevator shaft OK. |
| 03/06/2014 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
1. Twlve to sixteen feet at elevator shaft OK. |