Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/15/2013 |
PLUMBING - INTERMEDIATE |
|
Approved |
|
| 02/14/2013 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
1. Closet flange is to sit on top of finished floor. |
| 01/07/2013 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1. 1" PVC yardwater OK to cover. Install AVB on hose bibb. Gas pressure test OK. ABS DWV thru roof OK. PEX OK. Need to see closet flange after floor is set. |
| 12/28/2012 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1. ABS DWV underfloor OK. Water test one riser to ten feet. OK to cover. P.O.C. to existing under floor OK. |