Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 09/04/2013 |
PLUMBING - PROGRESS |
|
Approved |
|
| 08/30/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 07/24/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 07/19/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. N/H bldg. drain w/huskee bands extended to outside bldg. at Panther Hall. |
| 07/05/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 07/01/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. PVC DWV through the roof. Water piping in chase OK. |
| 06/25/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 06/24/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 06/20/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. At P.E. bldg restroom sewer and water connections made OK. At Girls Restroom #100 and #300 plumbing underground OK. At M.G. #114 and #115 plumbing OK. |
| 06/19/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Auditorium lobby and restrooms OK. #400 East Restroom OK. |
| 06/17/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. At P.E. restrooms- PVC DWV and copper in chase OK. |
| 06/14/2013 |
PLUMBING - PROGRESS |
|
Not ready for Inspection |
1. Entered on Yavapai. Gate locked. No one visible inside. |
| 06/07/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. 4" SDR-35 with tracer from tap at main to the two way cleanout fitting OK. Need to see the connection. |
| 05/14/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Gang Bathroom Panther Hall. Plumbing OK, Mechanical OK, Electric in walls only OK. #700 Restrooms rerough OK. |