Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
Permit Number - T12CM07840
Inspection Description - PLUMBING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2013 | PLUMBING - PROGRESS | Approved | ||
| 08/30/2013 | PLUMBING - PROGRESS | Partial Approval | ||
| 07/24/2013 | PLUMBING - PROGRESS | Partial Approval | ||
| 07/19/2013 | PLUMBING - PROGRESS | Partial Approval | 1. N/H bldg. drain w/huskee bands extended to outside bldg. at Panther Hall. | |
| 07/05/2013 | PLUMBING - PROGRESS | Partial Approval | ||
| 07/01/2013 | PLUMBING - PROGRESS | Partial Approval | 1. PVC DWV through the roof. Water piping in chase OK. | |
| 06/25/2013 | PLUMBING - PROGRESS | Partial Approval | ||
| 06/24/2013 | PLUMBING - PROGRESS | Partial Approval | ||
| 06/20/2013 | PLUMBING - PROGRESS | Partial Approval | 1. At P.E. bldg restroom sewer and water connections made OK. At Girls Restroom #100 and #300 plumbing underground OK. At M.G. #114 and #115 plumbing OK. | |
| 06/19/2013 | PLUMBING - PROGRESS | Partial Approval | 1. Auditorium lobby and restrooms OK. #400 East Restroom OK. | |
| 06/17/2013 | PLUMBING - PROGRESS | Partial Approval | 1. At P.E. restrooms- PVC DWV and copper in chase OK. | |
| 06/14/2013 | PLUMBING - PROGRESS | Not ready for Inspection | 1. Entered on Yavapai. Gate locked. No one visible inside. | |
| 06/07/2013 | PLUMBING - PROGRESS | Partial Approval | 1. 4" SDR-35 with tracer from tap at main to the two way cleanout fitting OK. Need to see the connection. | |
| 05/14/2013 | PLUMBING - PROGRESS | Partial Approval | 1. Gang Bathroom Panther Hall. Plumbing OK, Mechanical OK, Electric in walls only OK. #700 Restrooms rerough OK. |