Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2013 | FRAMING | Approved | IVRS - Inspection :* | |
| 09/04/2013 | FRAMING | Partial Approval | ||
| 08/27/2013 | FRAMING | Partial Approval | IVRS - Inspection :* | |
| 08/27/2013 | FRAMING | Partial Approval | 1. FRAMING AT 3RD FLOOR DUCT CHASE OK 2. PROVIDE HYDRO STATIC TEST ON ALL CHILL WATER PIPING |
|
| 07/24/2013 | FRAMING | Partial Approval | 1. OR-9 OK to rock one side. | |
| 07/11/2013 | FRAMING | Partial Approval | 1. Cutting penetrations for mechanical. Framing hard lid. Erected separation wall. | |
| 06/20/2013 | FRAMING | Partial Approval | 1. OR #08, Control, and OR #09. exterior walls framed and electric installed. |