Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T12CM07398
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/12/2013 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* | |
11/20/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/20/2013 | BUILDING PRE-SLAB | Partial Approval | TRUCK TURN-AROUND AREA - OK TO POUR | |
11/12/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/12/2013 | BUILDING PRE-SLAB | Partial Approval | 2 SLABS; ENVIRONMENT AREA GL: 1/J-J.25; CLEAR LANDING GL: 1/F.8-G; OK TO POUR | |
11/04/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/04/2013 | BUILDING PRE-SLAB | Partial Approval | SOUTH GARDEN CENTER SLAB GL: E.75-F.5/8-9; OK TO POUR SLAB | |
10/31/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* REBAR; 2 LIGHT POLE CORISSON FOOTINGS AT * |
|
10/25/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/16/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/16/2013 | BUILDING PRE-SLAB | Partial Approval | POUR #4 - OK TO POUR PROGRESS AREA | |
10/15/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/15/2013 | BUILDING PRE-SLAB | Partial Approval | POUR AREA #3 - OK TO POUR SLAB | |
10/14/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/14/2013 | BUILDING PRE-SLAB | Partial Approval | POUR #4 AND FREEZER SLAB (GL: 1/F-G) - OK TO POUR PROGRESS AREA | |
10/11/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/11/2013 | BUILDING PRE-SLAB | Partial Approval | LOADING DOCK SLABS AS PER DETAILS #5-6; PAGE S2 - OK TO POUR PROGRESS AREAS | |
10/10/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/10/2013 | BUILDING PRE-SLAB | Partial Approval | POUR AREA #2 - OK TO POUR PROGRESS AREA | |
10/09/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
10/07/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/07/2013 | BUILDING PRE-SLAB | Partial Approval | POUR AREA #1 - OK TO POUR | |
10/02/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
10/01/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
09/30/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
09/30/2013 | BUILDING PRE-SLAB | Not ready for Inspection | WILL RECALL FOR 10/1/13 | |
09/26/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
09/26/2013 | BUILDING PRE-SLAB | Partial Approval | EDC SLAB - OK TO POUR SLAB |